RMC No. 38-2015 publishes DBM MYOA rules requiring covered agencies to secure authority before multi-year contracts and bidding.
Government agencies, finance officers, budget officers, chief accountants, and contractors dealing with multi-year public projects must treat Multi-Year Obligational Authority as a required pre-contract and pre-bidding control. RMC No. 38-2015 publishes DBM Circular Letter No. 2015-7, which requires covered National Government Agencies, Constitutional Offices, and State Universities and Colleges to secure a MYOA before entering into contracts for the full project cost of multi-year programs, activities, and projects. For businesses bidding on government contracts, this matters because the MYOA becomes the reference for the Approved Budget for the Contract under procurement rules.
What Changed Under RMC No. 38-2015
RMC No. 38-2015 gives wide publicity to the updated DBM guidelines on the issuance of Multi-Year Obligational Authority, or MYOA. The central rule is that departments, bureaus, offices of the National Government, Constitutional Offices enjoying fiscal autonomy, and SUCs must request DBM issuance of a MYOA before entering into contracts covering the total project costs of multi-year programs, activities, and projects.
The rule applies whether the multi-year project is locally funded or foreign-assisted. It also covers multi-year contracts, lease arrangements, and lease-purchase agreements under the Revised Armed Forces of the Philippines Modernization Program under Republic Act No. 10349.
The MYOA is not merely an internal budget document. It is expressly identified as the basis or reference for the Approved Budget for the Contract, or ABC, referred to under Section 5 of Republic Act No. 9184, the Government Procurement Reform Act. For a multi-year project covered by a MYOA, the ABC is the amount reflected in the MYOA.
Why This Matters to Businesses, Contractors, and Finance Teams
For private contractors, suppliers, consultants, and service providers participating in government procurement, RMC No. 38-2015 is important because it links multi-year contracting authority with the procurement budget. A government agency should not proceed with bidding a multi-year contract unless the required MYOA has first been secured from DBM.
This is especially relevant for contractors bidding on infrastructure, information technology, communications equipment, lease-purchase, public-private partnership, foreign-assisted, or other long-term government projects. If the government procuring entity has no proper MYOA for a multi-year contract, the procurement process may face budgetary and authority issues before award or implementation.
For agency finance units, budget officers, and chief accountants, the circular confirms that future-year funding requirements must be aligned with the agencyβs Forward Estimates or Medium Term Expenditure Program. The MYOA is intended to ensure that succeeding funding requirements of the multi-year project are included in the budget program for the relevant year and remain within the total project cost and categories reflected in the applicable budget planning documents.
Who Is Covered by the MYOA Requirement
The circular covers all multi-year programs, activities, and projects implemented by National Government Agencies, Constitutional Offices, and SUCs. It applies to both capital and non-capital projects that will take more than one year to complete and require multi-year appropriations.
Capital expenditures or outlays include expenditures for goods and services whose benefits extend beyond the fiscal year and add to government assets. Non-capital expenditures refer to predictable and repeatable costs for goods and services used in normal government operations.
The circular also has specific relevance for the defense sector because it expressly includes multi-year contracts, lease agreements, and lease-purchase agreements under the Revised AFP Modernization Program.
Project Cost Thresholds and Required Evaluation
RMC No. 38-2015 publishes the cost thresholds for evaluating proposals for funding of capital and non-capital projects. Projects costing P1 billion and above, whether locally funded or foreign-assisted, including Public Private Partnership projects, are evaluated through the Investment Coordination Committee, INFRACOM, and the NEDA Board.
Projects costing less than P1 billion but from P300 million to less than P1 billion are evaluated by the Development Budget Coordination Committee Sub-Committee on Program/Project Appraisal. Projects costing less than P300 million are evaluated by the Department of Budget and Management.
These thresholds are important search points for CFOs, accountants, and government contractors reviewing MYOA requirements, government project cost approvals, DBM approval thresholds, and ABC rules for multi-year procurement.
Key Documentary Requirements for MYOA Issuance
Agencies requesting a MYOA must submit a request for MYOA, including confirmation of agency commitment, using the format prescribed by the circular. They must also submit a Funding Strategy or Medium Term Expenditure Program.
For projects costing P1 billion and above, approval by INFRACOM, the NEDA Board, or DBCC must be submitted when applicable. For projects below P1 billion, approval by the Agency Head is required, supported by a summary of project benefits, including economic viability and technical justification, and details of expected output and outcome.
For foreign-assisted projects, an approved loan agreement must be submitted when applicable. Agencies must also provide a certification from the Agency Head that procurement activity for the project covered by the MYOA has not yet started as of the date of request.
Other clearances must also be submitted when required by existing laws, policies, rules, and regulations. The circular specifically identifies DOST-ICTO endorsement for computerization projects, NTC clearance for acquisition of communication equipment, and DENR geo-hazard certification or project location documentation with a geo-tagged map or electronic photograph of the project location with certification.
Special Requirements for AFP Modernization Projects
For projects under the AFP Modernization Program, the circular requires approval of projects or activities by the President of the Philippines if the Revised AFP Modernization Program has not yet been endorsed to Congress. It also requires the approval issued by the President to the DND Secretary to enter into a multi-year contract for a specific acquisition or project.
The AFP-related requirements are in addition to the request for MYOA with agency commitment and the Funding Strategy or Medium Term Expenditure Program.
Budgeting Limits After MYOA Issuance
A MYOA does not automatically release funds or override the annual budget process. The annual requirement of the program or project must still be included in the proposed National Expenditure Program and remains subject to Congressional approval.
Agencies must include in their budget proposals submitted to DBM for the succeeding budget year the requirements of the program or project covered by the MYOA. The circular also provides a strict implementation limit: the obligation incurred in any given year shall in no case exceed the allotment released for that purpose during that year.
Effective Date and Compliance Consequences
DBM Circular Letter No. 2015-7 took effect immediately. RMC No. 38-2015 is dated June 9, 2015 and publishes the circular for the information and guidance of all concerned.
The issuance does not state a separate tax penalty or administrative fine for non-compliance. However, the practical compliance consequence is significant: agencies are required to secure MYOA before bidding and before entering into multi-year contracts, and the MYOA determines the ABC for multi-year projects. Non-compliance may therefore affect the authority, budgeting, and procurement basis of a government multi-year contract.
Practical Steps for Agencies and Contractors
Government agencies should review all proposed projects that will take more than one year to complete and determine whether they require multi-year appropriations. Before procurement activity starts, the agency should confirm the applicable cost threshold, secure the required project approvals, prepare the MYOA request, and complete the Funding Strategy or Medium Term Expenditure Program.
For capital expenditure projects, agencies should confirm inclusion in the Comprehensive Integrated Infrastructure Program or the Three-Year Rolling Infrastructure Program when applicable. Agencies should also check whether special endorsements or clearances are required, especially for computerization projects, communications equipment, and projects requiring geo-hazard or environmental location certifications.
Private contractors should ask, during procurement due diligence, whether the relevant multi-year government project has a MYOA and whether the ABC corresponds to the MYOA amount. This is particularly important for bidders on infrastructure projects, IT projects, communications equipment procurement, lease-purchase arrangements, PPP projects, and foreign-assisted projects.
How Ablola, Saribong & Gueco Can Help
RMC No. 38-2015 is a reminder that public procurement, government budgeting, and business compliance often intersect. Contractors bidding for government projects must understand not only tax and procurement rules, but also the budget authority supporting the contract.
Ablola, Saribong & Gueco advises corporations, suppliers, contractors, project proponents, and regulated businesses on BIR issuances, procurement compliance, government contracting, tax documentation, and corporate risk management. For assistance in reviewing government contract requirements, BIR compliance issues, or procurement-related documentation, visit MakatiLawFirm.com.