RMC No. 20-2013 published FY 2013 fund release rules, deadlines, NCA validity periods, and no-report no-release consequences for agencies and GOCCs.

Government agencies, LGUs, GOCCs receiving national budgetary support, and their budget and accounting units had to align FY 2013 fund requests, obligations, cash utilization, and report submissions with the fund-release rules under National Budget Circular No. 545, as published through RMC No. 20-2013. The most urgent compliance point was that appropriations and released allotments under the FY 2013 General Appropriations Act were available only up to December 31, 2013, while several requests and accountability reports had earlier cut-off dates that directly affected fund releases.

What RMC No. 20-2013 Changed

RMC No. 20-2013 published the full text of National Budget Circular No. 545, dated January 2, 2013, entitled Guidelines on the Release of Funds for FY 2013. Although issued by the Bureau of Internal Revenue for the information and guidance of internal revenue officials, employees, and others concerned, the circular reproduced the national government rules on the release, utilization, reporting, and accountability requirements for FY 2013 funds.

The circular implemented the FY 2013 Budget under Republic Act No. 10352, the FY 2013 General Appropriations Act. It provided the rules for Agency Budget Matrix releases, Special Allotment Release Orders, Notices of Cash Allocation, disbursement authorities, use of savings, use of excess income, and budgetary reporting. For government offices and entities supported by national funds, the circular was not merely informational. It affected whether funds would be released, whether allotments could be obligated, and whether agency heads could be held personally liable for improper payments.

Who Is Affected by RMC No. 20-2013

The primary affected entities were all government agencies, including local government units and government-owned or controlled corporations receiving budgetary support from the national government in FY 2013. The circular was also addressed to heads of departments, agencies, state universities and colleges, other national government offices, GOCCs, LGUs, budget officers, heads of accounting units, and all others concerned.

For private businesses, the circular mattered indirectly but practically. Suppliers, contractors, consultants, and service providers dealing with national government agencies had to understand that payment timelines could be affected by the validity of allotments, Notices of Cash Allocation, agency reporting compliance, and documentary requirements for prior-year accounts payable. Search phrases such as RMC No. 20-2013 fund release rules, FY 2013 budget release guidelines Philippines, no report no release policy DBM, SARO NCA deadlines 2013, and government accounts payable February 28 2013 are highly relevant to accountants, CFOs, and contractors reviewing government receivables.

Key Fund Release and Budget Rules

The FY 2013 General Appropriations Act took effect on January 1, 2013. All appropriations authorized under the FY 2013 GAA were available for release and obligation for the specified purposes, under applicable special provisions, only until the end of FY 2013. The circular expressly provided that unreleased appropriations and unobligated allotments would automatically lapse at the end of 2013.

Allotment releases for the year from all sources had to stay within the FY 2013 Allotment Release Program. Each national government agency’s Allotment Release Program was based on the agency’s specific budget under the FY 2013 GAA, plus automatic appropriations such as Retirement and Life Insurance Premiums, Special Accounts in the General Fund, and other items classified as automatic appropriations under the FY 2013 Budget of Expenditures and Sources of Financing.

Appropriations for agency-specific budgets, including automatic appropriations, were to be made available through the issuance of an Agency Budget Matrix or a Special Allotment Release Order. Funds, including allotments and disbursement authorities, were to be released directly to agencies and their operating units. Lump-sum appropriations could be released only after the agency submitted complete details or a list of sub-programs and activities with corresponding cost down to the lowest level, such as provincial, city, or municipal level, as applicable.

Important Deadlines and Validity Periods

The circular contained several specific deadlines that budget officers and accounting heads had to track. FY 2013 appropriations for Personal Services, Maintenance and Other Operating Expenses, and Capital Outlay under Republic Act No. 10352 were available for release only up to December 31, 2013. Released allotments were available for obligation only up to December 31, 2013. Programmed automatic appropriations were likewise available for release and obligation up to December 31, 2013.

For FY 2012 continuing appropriations, MOOE and Capital Outlay under Republic Act No. 10155 were available for release up to December 31, 2013. Unobligated balances of released allotments for MOOE and Capital Outlay in 2012, as of December 31, 2012, were available for obligation up to December 31, 2013.

The validity of Notices of Cash Allocation depended on the account and purpose. NCAs credited to Regular MDS Accounts for regular operations programmed for a specific month were valid only until the last working day of that month. NCAs credited to Special MDS Accounts for retirement gratuity, terminal leave benefits, and prior years’ accounts payable were valid until the last working day of the following month when the NCA was issued. NCAs for trust receipts credited to Trust MDS Accounts and NCAs issued to the Bureau of the Treasury for agency working funds were valid until the last working day of the year.

The circular also identified hard cut-off dates. November 30, 2012 was the deadline for agency submission of FY 2013 Budget Execution Documents. June 30, 2013 was the last day to submit requests for realignment of allotment under the FY 2012 Budget. November 15, 2013 was the last day to submit requests for releases requiring SAROs or additional NCAs in FY 2013. December 15, 2013 was the deadline to submit requests for use of excess income supported by Bureau of the Treasury certification.

No-Report, No-Release Policy

One of the most operationally important features of RMC No. 20-2013 was the strict enforcement of the no-report, no-release policy. The policy applied to the submission of Budget Execution Documents and Budget Accountability Reports. Failure to submit required reports could cause the DBM to defer or withhold additional releases.

The circular specifically linked quarterly Budget Accountability Reports to fund releases. BARs as of March 31, 2013, June 30, 2013, and September 30, 2013 affected the release of SAROs for the needing-clearance portion of the Agency Budget Matrix, and SARO or NCA releases for Personal Services deficiency for the filling up of positions. The DBM was also directed to post agency compliance with reportorial requirements on its website for public scrutiny.

Accounts Payable and Contractor Payment Implications

For agencies with prior years’ accounts payable, the circular required the List of Due and Demandable Accounts Payable as of December 31, 2012 to be submitted to the DBM not later than February 28, 2013. Separate lists had to be submitted for external and internal creditors.

This February 28, 2013 cut-off was especially important for contractors, suppliers, and service providers with receivables from government agencies. Prior-year due and demandable accounts payable not received by the DBM within the cut-off date would not be included in the special lane for priority funding. Instead, those payables would be queued under the normal payment procedure for current accounts payable and charged against NCAs under the Regular MDS Account using the Common Fund Scheme.

Realignment, Savings, and Use of Income

RMC No. 20-2013 emphasized that budgetary realignments during budget execution were generally not allowed, to avoid distorting original agency performance targets and the specific purposes authorized under the FY 2013 GAA. Appropriations had to be used for the purposes for which they were specifically authorized.

However, the circular recognized limited flexibilities. Agencies could augment items of expenditure within Personal Services, except that use of savings for Magna Carta benefits required prior DBM approval. Augmentation within MOOE was allowed, except Intelligence Funds, which required prior approval from the President. Realignment of savings from mandatory expenditures for petroleum, oil, lubricants, water, illumination, power services, telephone, other communication services, and rent was allowed only in the last quarter of the year and subject to applicable rules. Realignment of savings from one allotment class to another and among objects of expenditure within Capital Outlays required prior DBM approval.

Excess income could be used only when actual income collected and deposited with the Bureau of the Treasury exceeded the revenue estimates under the FY 2013 BESF. Agencies could request use of excess income as soon as they exceeded their revenue targets, but the request had to explain the reasons for generating excess revenues, such as new fees or charges not considered in the original revenue estimate. The deadline for requests for use of excess income supported by BTr certification was December 15, 2013.

Transparency and Website Posting Requirements

The circular also imposed transparency obligations. Agencies implementing infrastructure projects had to post on their websites, within thirty days from entering into a contract with the winning contractor, the project title, detailed description including nature and location, detailed estimates used in arriving at the Approved Budget for the Contract, and the winning contractor’s detailed bid estimates as awarded.

All agencies also had to maintain a transparency seal on their websites. The required disclosures included the agency mandate and functions, officials and contact information, annual reports for the last three years, approved budgets and corresponding targets, major programs and projects categorized under the five key results areas of Executive Order No. 43, programs and beneficiaries identified in applicable special provisions, and the annual procurement plan, contracts awarded, and names of contractors, suppliers, and consultants.

Consequences of Non-Compliance

The immediate operational consequence of non-compliance was delayed or withheld funding. Failure to submit required BARs could result in deferred or withheld additional releases. Failure to meet the February 28, 2013 cut-off for prior-year due and demandable accounts payable meant exclusion from the special lane for priority funding.

The circular also imposed a serious accountability consequence on agency leadership. The head of agency or operating unit would be held personally liable for any payment of expenditures not in accordance with the circular. This makes compliance not only a finance or accounting concern, but also a governance, audit, and personal accountability concern for agency heads and approving officers.

Practical Steps for Agencies, GOCCs, LGUs, and Businesses

Government agencies, GOCCs, and LGUs receiving national budget support should reconcile appropriations, allotments, obligations, NCAs, and payables against the validity periods and cut-off dates stated in RMC No. 20-2013. Budget and accounting units should verify whether requests requiring SAROs, additional NCAs, realignments, or use of excess income were supported by the required financial plans, physical plans, lists of implementing operating units, and Bureau of the Treasury certifications.

Agency heads should require internal compliance checks before approving payments, especially where the transaction involves prior-year accounts payable, savings, excess income, procurement items requiring prior clearance, or needing-clearance portions of the Agency Budget Matrix. Contractors and suppliers dealing with government agencies should also confirm whether their receivables were included in the required accounts payable lists and whether the agency had valid disbursement authority to pay.

How Ablola, Saribong & Gueco Can Help

RMC No. 20-2013 is a reminder that government finance rules can directly affect tax administration, public procurement, receivables collection, audit exposure, and management accountability. Ablola, Saribong & Gueco advises businesses, contractors, government-facing suppliers, and regulated entities on BIR compliance, government transactions, fund-release documentation, receivables strategy, and dispute prevention.

For assistance in reviewing BIR issuances, government receivables, budget-linked payment issues, or compliance exposure involving Philippine tax and public finance rules, contact Ablola, Saribong & Gueco through MakatiLawFirm.com.


Leave a Comment

Your email address will not be published. Required fields are marked *