RMO No. 29-2010 standardizes BIR procurement money claim processing, requiring complete documents, inspection, voucher review, and COA clearance when applicable.
Suppliers, contractors, project proponents, and BIR offices handling procurement-related claims must follow a standardized documentary and routing process before payment can be approved. RMO No. 29-2010 makes completeness of supporting documents, inspection and acceptance, accounting review, and COA pre-audit clearance, when applicable, mandatory conditions for the payment of certain money claims arising from procurement of goods, consulting services, infrastructure projects, job orders, purchase orders, and contracts.
What RMO No. 29-2010 Changed
RMO No. 29-2010 prescribes uniform guidelines and procedures for processing and paying certain money claims involving BIR procurement transactions. The issuance was adopted after the approval and implementation of the customized BIR Procurement Manual on May 31, 2007, which introduced changes in the procurement of goods, consulting services, and infrastructure projects with contracts.
The central change is standardization. Before a money claim can be paid, it must be supported by the complete documentary requirements listed in the applicable Checklist of Requirements under Annexes A to M. The Order also assigns specific responsibilities to the General Services Division, Administrative Division, Inspection and Acceptance Committee, Regional Inspection and Acceptance Committee, Project Proponent, Procurement Division, Accounting Division, Finance Division, Financial Service, Office of the Assistant Regional Director, Administrative Service, COA Resident Auditor, and other concerned offices.
For businesses dealing with BIR procurement, the practical consequence is straightforward: payment is not merely a matter of sending an invoice. The claim must pass through receipt of deliverables, inspection, acceptance, documentary verification, preparation of the Disbursement Voucher, accounting and finance review, approval, check preparation, countersigning, and release, with additional COA pre-audit requirements when applicable.
Who Is Affected by RMO No. 29-2010
RMO No. 29-2010 directly affects suppliers, contractors, service providers, consultants, and infrastructure contractors with procurement contracts, purchase orders, job orders, or similar arrangements with the BIR. It is particularly relevant to businesses providing goods, consulting services, infrastructure projects, security services, janitorial services, telecommunications services, printing of tax forms, comprehensive lease of IT equipment, and other IT services.
The issuance also affects internal BIR project proponents and administrative offices because it imposes strict internal deadlines for receiving documents, requesting inspection, forwarding invoices, preparing vouchers, verifying completeness, and returning deficient claims. For corporate accountants and finance officers transacting with the BIR, this Order is important because payment delays may arise from incomplete billing documents, missing inspection reports, lack of acceptance, or absence of the required authority for a representative to receive checks.
Key Documentary and Compliance Requirements
The most important rule under RMO No. 29-2010 is that no money claim shall be approved for payment unless it is duly supported by complete documentary requirements specified in the applicable Checklist of Requirements under Annexes A to M. The responsible officer of the office involved must ensure the correctness and completeness of the documents supporting the claim.
Purchases made by the BIR must be inspected and verified by the Inspection and Acceptance Committee. The IAC determines whether deliveries conform with the specifications, terms, and conditions stated in the purchase order, job order, or contract. Only the IAC is authorized to conduct the inspection and issue the corresponding Inspection and Acceptance Report.
Where inspection is required under existing rules and regulations, no money claim may be paid until evidence of satisfactory inspection by the IAC is attached to the claim. In addition, money claims subject to pre-audit by the Commission on Audit may be paid only after a favorable audit action by the COA Auditor.
Important Processing Deadlines Under RMO No. 29-2010
The Order sets several operational deadlines that businesses and BIR offices must observe. The General Services Division or Administrative Division must prepare the Request for Inspection, together with photocopies of the Delivery Receipt, Sales Invoice, Service Invoice, or Charge Invoice, and forward the same to the IAC Chairman and COA within twenty-four hours from receipt of deliveries.
The original Delivery Receipt, Sales Invoice, Service Invoice, or Charge Invoice must be forwarded to the Procurement Division within twenty-four hours from the conduct of actual inspection. Certified photocopies must also be submitted to the Accounting Division or Finance Division for inventory recording within twenty-four hours from receipt of deliveries.
The IAC or RIAC must conduct actual inspection of deliveries within three working days from receipt of the request for inspection. It must prepare and submit the duly signed Inspection and Acceptance Report, together with the Inspector’s Report, to the Procurement Division or Administrative Division within two working days from conduct of inspection or reinspection. If there is a deficiency or non-conformity, the report must be returned within one day from discovery of the discrepancy.
The Project Proponent must prepare and submit the Billing Statement, Sales Invoice, Statement of Account, checklist, and supporting documents to the Procurement Division or Administrative Division within two working days from receipt of the billing document or from return of the claim due to lacking requirements. For goods or services directly delivered to the Project Proponent, such as applications, licenses, reports, documentation, manuals, and similar deliverables, the Project Proponent must prepare and submit the Request for Inspection within twenty-four hours from receipt of the contract deliverables.
The Procurement Division or Administrative Division must verify completeness of supporting documents within three working days from receipt. If the documents are complete and compliant with the job order, purchase order, or contract, it must evaluate correctness and accuracy and prepare the Disbursement Voucher within four working days from receipt of all required documents. The Disbursement Voucher and supporting documents must be transmitted to the Accounting Division or Finance Division within one day after preparation.
The Accounting Division or Finance Division must verify completeness, accuracy, propriety, validity, and legality of all money claims within a maximum of five working days from receipt. For security, janitorial and other manpower deployment contracts, telecommunications, printing of tax forms directly delivered to Regional or District Offices, comprehensive lease of IT equipment, and other IT services, the processing period is seven working days from receipt of the Disbursement Voucher.
After processing, the money claim must be indexed within one hour. The Accounting Division or Finance Division must certify availability of cash and completeness of supporting documents within two working days after evaluation and then forward the certified Disbursement Voucher and supporting documents to the Financial Service or Office of the Assistant Regional Director.
The Financial Service or Office of the Assistant Regional Director must review the Disbursement Voucher within a maximum of two working days from receipt. For the special categories of claims involving manpower deployment, telecommunications, printing of tax forms, comprehensive lease of IT equipment, and other IT services, the review period is three working days. Payment approval must be made within two working days after review.
COA Pre-Audit and Check Release Requirements
If the money claim is not subject to COA pre-audit, the approved Disbursement Voucher is forwarded to the General Services Division or Administrative Division. If it is subject to pre-audit under COA Circular Nos. 2009-02 and 2009-05, it must be forwarded to the COA Resident Auditor. If COA gives favorable action, the Financial Service or Assistant Regional Director forwards the documents to the General Services Division or Administrative Division within one working day from approval of the Disbursement Voucher for check preparation.
The General Services Division or Administrative Division must prepare, sign, and countersign the check within one working day from receipt of the approved Disbursement Voucher. The signed check and supporting documents are then forwarded to the Administrative Service or Assistant Regional Director for countersigning. The Administrative Service or Assistant Regional Director must countersign the check within one working day from receipt and return it to the General Services Division or Administrative Division.
Before release of the check, the claimant or duly authorized representative must submit an Official Receipt acknowledging payment of the claim, a Special Power of Attorney executed by the payee authorizing the representative to claim the check, a Board Resolution authorizing the representative to receive the check if applicable, and a proper identification card of the claimant or authorized representative. The Advice of Checks Issued and Cancelled must be prepared, signed, and submitted to the Land Bank of the Philippines and Bureau of the Treasury within the day of preparation of the check.
Deficiencies, Returned Claims, and Payment Delays
RMO No. 29-2010 does not create a separate monetary penalty schedule for suppliers or contractors. However, it imposes a strict operational consequence: claims with findings, deficiencies, or lacking requirements must be returned by the office that discovered the issue within one working day. This means incomplete invoices, missing inspection documents, non-conforming deliverables, unsigned reports, unsupported vouchers, or inadequate authority documents can immediately stop the payment process.
For businesses, the risk is cash-flow delay. A supplier or contractor that fails to align its billing documents with the BIR’s checklist and inspection requirements may experience repeated returns of its claim, deferred voucher preparation, delayed accounting review, and non-release of payment until deficiencies are cured.
Practical Steps for Suppliers, Contractors, and Finance Teams
Businesses transacting with the BIR should treat RMO No. 29-2010 as a payment-readiness checklist. Before submitting any claim, the supplier or contractor should confirm that the billing statement, sales invoice, statement of account, service invoice, charge invoice, delivery receipt, contract documents, inspection documents, and acceptance requirements are complete and consistent with the purchase order, job order, or contract.
Finance teams should also coordinate early with the BIR project proponent to confirm which Annex A to M checklist applies to the specific claim. They should monitor the twenty-four-hour inspection request period, the three-working-day inspection period, the two-working-day IAR submission period, and the internal processing periods for the Disbursement Voucher and finance review. For representatives claiming checks, the Official Receipt, Special Power of Attorney, Board Resolution if applicable, and proper identification should be prepared before the check release stage.
Common search issues related to this issuance include BIR procurement money claims, BIR payment processing requirements, Inspection and Acceptance Report for BIR suppliers, Disbursement Voucher processing BIR, COA pre-audit BIR claims, and BIR check release requirements. These are the practical areas where compliance problems usually arise.
Effectivity of RMO No. 29-2010
RMO No. 29-2010 took effect immediately. It also amended or modified all revenue memorandum orders and circulars inconsistent with its provisions. For procurement-related money claims covered by the issuance, compliance with the prescribed routing, inspection, documentary, voucher, audit, and check release requirements is required before payment may be made.
How Ablola, Saribong & Gueco Can Help
Ablola, Saribong & Gueco advises suppliers, contractors, service providers, corporate finance teams, and regulated businesses on BIR compliance, procurement documentation, government contract payment issues, tax administration, and audit-related concerns. For companies dealing with BIR procurement claims, delayed payments, documentary deficiencies, COA pre-audit issues, or disputes arising from inspection and acceptance requirements, our team can review the transaction documents, identify compliance gaps, and prepare corrective submissions.
For assistance with BIR compliance, tax administration, procurement-related claims, and government payment documentation, contact Ablola, Saribong & Gueco through MakatiLawFirm.com.