BIR offices, project proponents, procurement units, and regional administrative divisions must publicly disclose every BIR program, project, and activity, regardless of amount or funding source, and must submit annual and monthly reports to COA within strict internal deadlines. RMO No. 18-2014 matters to businesses because it affects transparency in BIR procurement, awarded projects, infrastructure postings, and the audit treatment of project expenses. Contractors, suppliers, consultants, and other private parties dealing with BIR projects should expect more visible project information, stricter reporting discipline, and possible audit disallowance where the required publicity and reporting rules are not followed.

What RMO No. 18-2014 Changed

RMO No. 18-2014 prescribed the BIR guidelines and procedures for implementing the information and publicity requirements under COA Circular No. 2013-004 dated January 30, 2013. Its central rule is full disclosure: all BIR programs, projects, and activities, referred to as PPAs, must be reported and posted, whether they are ongoing, newly implemented, infrastructure-related, locally funded, or supported by foreign development agencies.

The Order requires the BIR to submit, at the beginning of each year, a consolidated list of PPAs to the Commission on Audit. This list must include both ongoing PPAs and those to be implemented during the year. The rule is not limited by project size. The Order expressly states that all PPAs shall be posted, regardless of the amount or source of funds. This is the most important compliance point for BIR offices and project proponents: even small projects and activities must be included in the publicity and reporting system.

For businesses searching for BIR project posting requirements, COA Circular 2013-004 implementation, BIR awarded projects report, BIR infrastructure signboard rules, or RMO 18-2014 compliance deadlines, the practical effect is that BIR project information is no longer treated as merely internal. The Order creates a documented reporting and publication trail from the project proponent, to the approving officials, to the Planning and Programming Division or Administrative Division, to publication, and finally to COA or the Regional Audit Team Leader.

Who Is Affected

The direct addressees are all internal revenue officials, employees, and others concerned. Within the BIR, the Order affects project proponents, Deputy Commissioners, the Chief of Staff of the Office of the Commissioner, Assistant Commissioners, Regional Directors, Assistant Regional Directors, the Procurement Division, the Planning and Programming Division, the General Services Division, and the Administrative Divisions in the Revenue Regional Offices.

Although the Order is primarily an internal BIR governance issuance, it is relevant to private contractors, suppliers, service providers, consultants, and infrastructure contractors dealing with BIR projects. Awarded projects must be reported monthly, and infrastructure projects require physical signboards at the project location. A contractor that receives a Notice of Award for an infrastructure project should expect project publicity within five days from receipt of the Notice of Award.

The Order is also relevant to accountants, compliance officers, and corporate governance personnel monitoring public procurement and government project transparency. It does not impose a new tax rate, tax return deadline, or taxpayer filing requirement. Its significance lies in BIR transparency, COA audit compliance, public notice requirements, and the risk that project expenses may be disallowed in audit if the Order is violated.

Key Posting and Publicity Requirements

RMO No. 18-2014 requires information about each PPA to be posted on signboards located in conspicuous places within office premises. The term signboards is broad and includes signboards, blackboards, whiteboards, posters, tarpaulins, streamers, electronic boards, and similar materials. For ordinary PPAs, the signboards must not exceed three feet by two feet.

The signboards must contain the project details required by the prescribed format. For PPAs whose implementation period does not exceed five days, the project details may be omitted, except for the start and end dates of the PPA. This short-duration exception is narrow: it reduces the project details to be posted, but it does not remove the obligation to disclose the PPA’s start and end dates.

For PPAs funded through assistance from foreign development agencies, the name and logo of the foreign development agencies must be prominently displayed or printed in the signboards and public notices. This matters for donor-funded and development-assistance projects because the source of support must be visible in the public disclosure materials.

For infrastructure projects, tarpaulin signboards must be posted or displayed at the project location within five days from receipt of the Notice of Award by the contractor. The signboard must be suitably framed for outdoor display. The specified format is a white signboard measuring eight feet by eight feet, with 70 dpi resolution, Helvetica font, black font color, main information font size of three inches, and sub-information font size of one inch. In localities where tarpaulins are unavailable, any material may be used to prepare the required signboards for publication purposes.

The Order also prohibits personality-driven project publicity. No signboard may display or be affixed with the picture, image, motto, logo, color motif, initials, or other symbol or graphic representation associated with the top leadership of the project proponent or any person associated with the project proponent. This rule reinforces that public notices should disclose project information, not promote officials or personalities.

Key Compliance Deadlines

Project proponents must prepare and submit the List of On-Going PPAs, using the format prescribed in Annex A, in printout and softcopy using MS Excel, on or before the third day after the close of the year. The Monthly Project Status Report, using the format prescribed in Annex B, must be submitted in printout and softcopy using MS PowerPoint on or before the third day after the close of each month. The Report on Awarded Projects for all projects awarded during the month must also be submitted on or before the third day after the close of each month.

After approval, the same reports must be submitted by project proponents to the Planning and Programming Division for National Office projects or to the Administrative Division for Regional Office projects. The approved List of On-Going PPAs must be submitted on or before the sixth day after the close of the year. The approved Monthly Project Status Report and Report on Awarded Projects must be submitted on or before the sixth day after the close of each month.

For the National Office, the Procurement Division must submit to the Planning and Programming Division the List of PPAs to be implemented during the year, based on the approved Annual Procurement Plan, on or before the fifth day after the close of the year. The Planning and Programming Division must prepare and submit the National Office consolidated list for the Commissioner’s signature on or before the twelfth day after the close of each year, and submit the consolidated list to the COA Supervising Auditor, together with the General Services Division’s Notice of Publication, on or before the fifteenth day after the close of each year.

Monthly National Office reports follow a similar timeline. The Planning and Programming Division must consolidate the monthly Project Status Reports and Reports on Awarded Projects and transmit a softcopy to the General Services Division for electronic board publication on or before the tenth day after the close of each month. The transmittal package for the Commissioner’s signature must be prepared on or before the twelfth day after the close of each month. Submission to the COA Supervising Auditor, copy furnished the Budget Division, must be made on or before the fifteenth day after the close of each month.

For Revenue Regional Offices, the Administrative Division must submit the consolidated annual list to the Regional Audit Team Leader, together with the Notice of Publication, on or before the fifteenth day after the close of each year. Monthly Project Status Reports and Reports on Awarded Projects must be published on or before the tenth day after the close of each month, with written notification of publication submitted within two days from publication. The monthly consolidated reports and notice of publication must be submitted to the Regional Audit Team Leader, copy furnished the Finance Division, on or before the fifteenth day after the close of each month.

Penalties and Audit Consequences

Non-compliance with the prescribed deadlines for submission of reports and other documents is treated as a violation of reasonable office rules and regulations under Section 43 of the Revised Code of Conduct for Revenue Officials and Employees under RMO No. 53-2010. The stated penalties are reprimand for the first offense, suspension for one to thirty days for the second offense, and dismissal for the third offense.

The more serious financial consequence is audit disallowance. RMO No. 18-2014 states that in case of violation of the Order, all expenses incurred in relation to a particular project shall be disallowed in audit. This means the failure to comply with publicity and reporting requirements can affect the allowability of project expenses, not merely the internal administrative liability of the personnel involved.

Practical Steps for Compliance

BIR offices and project proponents should maintain a year-end and monthly reporting calendar keyed to the third, fifth, sixth, tenth, twelfth, and fifteenth day after the close of the relevant period. The annual PPA list, monthly Project Status Report, and monthly Report on Awarded Projects should be prepared in the required formats and routed early enough to allow approval, consolidation, publication, and COA submission within the stated deadlines.

For procurement and infrastructure-related projects, the Notice of Award date should be tracked carefully because infrastructure signboards must be posted within five days from the contractor’s receipt of the Notice of Award. Contractors and suppliers should also ensure that project details appearing in public notices are consistent with the award documents and implementation records.

Offices should also review signboard layouts before posting. The signboard must disclose the required project information, comply with size and formatting requirements where applicable, and avoid prohibited images, logos, initials, mottos, color motifs, or other symbols associated with officials or project proponents. For foreign-assisted PPAs, the foreign development agency’s name and logo must be prominently displayed.

How Ablola, Saribong & Gueco Can Help

RMO No. 18-2014 is not a taxpayer assessment rule, but it is important for procurement transparency, COA audit compliance, government project documentation, and parties dealing with BIR programs and awarded projects. A missed report, late publication, defective signboard, or incomplete notice can create administrative exposure and audit disallowance risks.

Ablola, Saribong & Gueco assists businesses, contractors, suppliers, regulated entities, and corporate clients in navigating BIR compliance, government procurement documentation, COA-related audit issues, tax risk management, and regulatory reporting. For guidance on BIR issuances, tax compliance, government contracts, and audit-sensitive documentation, contact Ablola, Saribong & Gueco through MakatiLawFirm.com.